Announced vs delivered, with receipts. A free, public, per-site event ledger of the AI data center buildout — every transition dated and sourced. Undisclosed is an honest value, not a gap.
Independence, Missouri, USA
Lancaster, Pennsylvania, USA
Montreal, Quebec, Canada
United States (site not named)
Abilene, Texas, USA
Vineland, New Jersey, USA
Kenilworth, New Jersey, USA
Montreal, Quebec, Canada
Memphis, Tennessee, USA
Port Washington, Wisconsin, USA
San Jose, California, USA
El Paso, Texas, USA
Bridgeport, Alabama, USA
Trenton, Ohio, USA
| Ticker | Company claim | Observable | Gap | Note |
|---|---|---|---|---|
| NBIS | 2.5 GW contracted power by end-2026 (Zacks) | Independence KS site prep (1 campus); 300 MW Bloom fuel-cell site announced | Majority of contracted GW not yet observable at named sites | Burry short; backlog conversion is the market debate |
| CRWV | 14 DCs / 2,110 MW across 10 US states (usdatamap) | Lancaster PA: announced Jul 2025, no groundbreaking found | Lancaster 100MW of 2,110MW — thin physical evidence for a $6B commitment | Delays already triggered sell-off (Bisnow) |
| WYFI | MTL-1 operational 4 MW gross (Q2 filing) | Confirmed: 4 MW operational, Tier-3 | MTL-2 (Q4 2025 target) slipped ~1 month | Only disclosed site is in Canada |
| AGPU | $260M B300 contract + $1.5B Blackwell contract | Contracts signed; NO site physically observable — site undisclosed | 100% of claimed capacity is unobservable | Honest 'undisclosed' display is the whole discipline |
| xAI | 2 GW total capacity, 555k GPUs (~$18B) by 2026 | Colossus 2 operational: 946 MW IT, ~1.1M H100-eq (Epoch) | 59 unpermitted turbines; NAACP/SELC suit + DOJ intervention | Fastest build in history; permitting friction is the story |
| META | $10B+, 1 GW by 2028 (El Paso) | Groundbreaking Oct 2025; $14B BlackRock JV Jul 2026 | 366MW gas plant pending PUC review | BlackRock JV = new financing pattern for AI DCs |
| GOOGL | $1.5B expansion 2026-27 (Jackson County) | Construction starting Jun 2026 after ~2-yr delay | 300MW+ TVA contract not yet online | Delayed 2 years — delay itself is the signal |
| MSFT | 48MW phase 1, expandable ~99MW (Alviso) | Groundbreaking Jun 2026; completion targeted 2028 | Utility agreement undisclosed | Revived after 6-year stall |
| AMZN | $5B Trenton project (Prologis) | Zoning + tax abatement approved; Amazon confirmed Aug 2026 | Annexation in dispute; no groundbreaking | AWS rarely announces — watch the permits |